Anambra State Productive Energy Development Bill

A framework for mini-grids, solar systems, battery storage and public-building solarisation, sequenced from markets and public facilities to productive clusters and digital infrastructure.

Version 0.2Published 2026-08-01Target year 2027
Download PDF

Legislative Stage

✓
Idea
✓
Research
3
Draft
4
Consultation
5
Introduced
6
Committee
7
Debate
8
Passed
9
Assent
10
Implementation
11
Review

Purpose

To create a structured framework for deploying mini-grids, solar systems, battery storage and productive-use energy solutions in Anambra State, prioritised by economic use.

Problem Statement

Unreliable and expensive power is one of the largest hidden costs for small businesses across Anambra State, limiting operating hours, spoiling perishable goods and raising production costs relative to better-served areas.

Legislative Objectives

  • Establish a framework for mini-grid, solar and battery-storage deployment prioritised by productive use.
  • Sequence deployment: markets and public facilities first, then productive clusters, then digital and technology facilities.
  • Encourage private and development-partner investment in generation and distribution.
  • Support SME adoption of productive-use energy systems.

Definitions

Productive-Use Energy
Energy systems sized and sited to directly support commercial or productive activity, as distinct from purely residential lighting.
Mini-Grid
A small-scale, localised electricity generation and distribution system serving a defined cluster of users.

Proposed Provisions

  1. 1.A statutory Productive Energy Plan, revised every three years, setting a phased deployment framework: Phase 1 markets and public facilities; Phase 2 productive clusters; Phase 3 digital and technology facilities; Phase 4 future economic-cluster infrastructure.
  2. 2.Criteria for prioritising sites by economic use and number of businesses served.
  3. 3.A mechanism for private-sector and development-partner co-investment in generation and distribution assets.
  4. 4.An energy audit of every primary healthcare centre, public secondary school and technical college, and a published schedule to solarise them, with a maintenance contract for every installation.
  5. 5.A one-stop permit process for mini-grid and solar developers on State land and roads, with applications decided within 60 days.
  6. 6.Consumer protection for mini-grid customers: published tariffs, metering and a complaints route.
  7. 7.An annual report to the House of Assembly on sites electrified, capacity installed and permits decided.

Institutional Responsibilities

  • Relevant State ministry responsible for power and energy, coordinating statewide site prioritisation with the Rural Electrification Agency and licensed mini-grid operators.
  • Office of the Member representing Nnewi South I to advocate for local site prioritisation.
  • Market associations and productive-cluster representatives as demand-aggregation partners.

Financing Implications

Primarily structured around private and development-finance investment (development banks, renewable-energy investors, the Rural Electrification Agency's Nigeria Electrification Project and similar programmes), with government's role focused on site identification, demand aggregation and regulatory facilitation rather than direct asset ownership.

Implementation Mechanism

2027: site assessment and demand aggregation at priority markets. 2028: first mini-grid and solar pilots at markets and public facilities, sequenced with the Power for Production Programme.

Monitoring Mechanism

Tracked under the Power category of the Accountability Dashboard: facilities electrified, productive clusters supported, renewable capacity installed.

Implementation Tracker

The deadlines this Bill writes into law, counted from commencement. Once the Bill is passed, each milestone is tracked here and on the Accountability Dashboard until it is met.

MilestoneDueResponsibleStatus
Productive Energy Plan published, with ranked priority sitesWithin 9 months of commencementCommissioner for PowerNot started
Energy audit of every PHC, public secondary school and technical college publishedWithin 12 monthsMinistry of PowerNot started
Public-building solarisation schedule laid before the HouseWithin 12 monthsMinistry of PowerNot started
Mini-grid permits decided within the 60-day statutory limitFrom commencement, reported annuallyMinistry of Power; Ministry of LandsNot started
Annual Productive Energy report laid before the HouseBy 31 March each yearCommissioner for PowerNot started

Expected Outcomes

  • Markets and public facilities with power reliable enough to extend operating hours.
  • Reduced energy costs for participating small businesses.
  • A pipeline of bankable energy projects for development-partner and private investment.

Legal Considerations

This proposal is intended to operate within the legislative competence of the Anambra State House of Assembly and in conformity with applicable federal law, including the Constitution of the Federal Republic of Nigeria, the Land Use Act, the Public Procurement Act and relevant sector legislation. Final drafting will be reviewed by legislative counsel prior to introduction. Energy generation and distribution activity will be structured to comply with applicable Electric Power Sector Reform Act provisions and Nigerian Electricity Regulatory Commission requirements for mini-grid and embedded-generation licensing.

Draft Text of the Bill

Pre-introduction draft for public comment. Legislative counsel will settle the final text before the Bill is introduced.

Anambra State Productive Energy Development Law, 2027

A Bill for a Law to Provide for the Planned Development of Electricity for Productive Use in Anambra State, to Require the Solarisation of Public Health Centres and Schools, to Facilitate Mini-Grid and Embedded Generation Projects, to Protect Mini-Grid Customers, and for Related Matters.

BE IT ENACTED by the House of Assembly of Anambra State of Nigeria as follows:

Part I: Preliminary

1. Citation and commencement

  1. (1)This Law may be cited as the Anambra State Productive Energy Development Law, 2027.
  2. (2)This Law shall come into force on the date the Governor assents to it.

2. Interpretation

In this Law: “Commissioner” means the Commissioner responsible for power; “Ministry” means the Ministry responsible for power; “Regulator” means the electricity regulatory authority for the State established under the State electricity law in force or, until such authority is established, the Nigerian Electricity Regulatory Commission; “mini-grid” means an electricity generation and distribution system serving a defined cluster of customers, whether or not connected to the national grid; “productive use” means the use of electricity to support commercial, agricultural, industrial or other income-generating activity; “priority site” means a site designated under section 5; “public facility” means a primary healthcare centre, public secondary school, technical college or other building owned by the State or a Local Government Council and used to deliver a public service.

3. Relationship with other laws

This Law shall be read together with the Electricity Act, 2023 and any State electricity law, and nothing in it confers a licence to generate, distribute or sell electricity, which shall be obtained from the Regulator in the ordinary way.

Part II: Productive Energy Plan

4. Productive Energy Plan

  1. (1)The Commissioner shall, within nine months of the commencement of this Law and every three years thereafter, prepare and publish a Productive Energy Plan for the State.
  2. (2)The Plan shall set out: (a) the communities, markets and production clusters without electricity or with inadequate supply; (b) the priority sites under section 5, in ranked order; (c) the projects proposed for each priority site, whether grid extension, mini-grid or standalone solar; (d) the expected source of finance for each project; and (e) a timetable.
  3. (3)Before publishing the Plan, the Commissioner shall consult the electricity distribution company for the State, the Rural Electrification Agency, market associations, Local Government Councils and members of the public.

5. Priority sites

  1. (1)Sites shall be ranked for the purposes of the Plan by reference to published criteria, which shall include: (a) the number of businesses and workers who would use the electricity; (b) whether the site is a market, workshop cluster, agro-processing site or other centre of production; (c) the existing cost and reliability of supply; and (d) whether the site includes public facilities.
  2. (2)Deployment shall be sequenced, as far as practicable: first, markets and public facilities; second, productive clusters; third, digital and technology facilities.
  3. (3)The data used to rank sites shall be published with the Plan.

Part III: Public Facilities

6. Energy audit of public facilities

The Ministry shall, within twelve months of the commencement of this Law, carry out and publish an energy audit of every primary healthcare centre, public secondary school and technical college in the State, stating the electricity each needs and the reliability of its present supply.

7. Solarisation schedule

  1. (1)On the basis of the audit, the Commissioner shall lay before the House of Assembly a schedule for installing solar power with battery storage, or another reliable supply, at every public facility that lacks one, giving priority to primary healthcare centres offering maternity services.
  2. (2)Every installation under this section shall be accompanied by a maintenance arrangement for not less than five years, funded at the time of installation.
  3. (3)The schedule shall be implemented subject to appropriation and to any co-financing obtained from development partners or federal programmes.

Part IV: Facilitating Investment

8. One-stop permits

  1. (1)The Ministry shall coordinate, as a single point of contact, every State approval needed to build a mini-grid or solar project, including approvals for the use of State land, rights of way along State roads, and building and environmental approvals.
  2. (2)An application under subsection (1) shall be decided within sixty days of its complete submission, and where it is refused, the reasons shall be given in writing.

9. Use of public land and roofs

The Commissioner may, with the approval of the Executive Council and under the Land Use Act, make State land or the roofs of public buildings available to a licensed developer for a mini-grid or solar project at a concessionary rent, on terms published in advance.

10. Demand aggregation

  1. (1)The Ministry may work with market associations, cooperatives and Local Government Councils to aggregate demand at a priority site, so that projects can be financed by private investors, development-finance institutions or the Rural Electrification Agency.
  2. (2)Nothing in this Law requires the State to own, operate or guarantee the revenue of any generation or distribution asset.

Part V: Customer Protection

11. Mini-grid customers

  1. (1)A mini-grid operator serving a priority site facilitated under this Law shall: (a) publish its tariffs; (b) meter every customer; (c) give each customer a written statement of the terms of supply; and (d) operate a complaints procedure.
  2. (2)A customer who is dissatisfied with the outcome of a complaint may refer it to the Regulator.

Part VI: Miscellaneous

12. Annual report

The Commissioner shall, not later than 31 March of each year, lay before the House of Assembly a report stating, for the preceding year, the progress made against the Productive Energy Plan, the public facilities connected or solarised, the capacity installed, the permits applied for and decided under section 8 and the time taken, and the finance mobilised.

13. Regulations

The Commissioner may make regulations for giving effect to this Law.

Explanatory Memorandum

(This memorandum does not form part of the Law. It summarises its purpose.)

This Law makes power for production a planned, published programme rather than a series of one-off projects. It requires a Productive Energy Plan that ranks sites by how many businesses and workers will benefit, an energy audit and solarisation schedule for health centres and schools, a 60-day one-stop permit process for mini-grid investors, and basic protection for mini-grid customers. It does not make the State an electricity company; investment is expected to come from private developers, development-finance institutions and the Rural Electrification Agency.

Public Consultation Status

Not yet opened for formal public consultation. This is a pre-legislative policy proposal, published for public comment ahead of introduction to the Anambra State House of Assembly following the 2027 legislative calendar.

View the Public Consultation Archive →
ⓘ

This is a proposed bill, drafted to apply statewide across Anambra State, not enacted legislation. It should not be represented as law unless and until it is passed by the Anambra State House of Assembly and formally assented to.